Supply Chain Issues

Having a partnership with your commercial roofing contractor is  now more important than ever!!!  Supply chains are in crisis, here is how it is directly impacting the roofing industry.


Commercial Roofing Applications (Flat or Low slope):

Components:

  • Roofing Board Insulation (all types) 10-12 month lead times / smaller quantities are available in limited supply

  • Roofing Fasteners and plates (all types) 10-12 month lead times / smaller quantities are available in limited supply

  • Roofing Adhesives and bonding agents 6-10 month lead times

  • Roof Coatings – liquid applied roof systems 2 month lead times

 
Membranes & Roof Coverings:

  • Single ply membranes (TPO, PVC, & EPDM) – Sold out for calendar year 2022! Smaller quantities are available in limited supply all orders placed today through the end of the year are scheduled for delivery in 2023  with no delivery date!

  • Modified bitumen membranes are 1-2 month lead times  based on the job size and needs


Residential Roofing Application (Steep Slope)

  • Asphalt Shingles- have limited color pallet selection with 1-2 month lead times.  

  • Concrete & Clay Roof Tile – standard color selections with 11- 12 months lead times.

  • Metal Roof Panels –   are the most readily available of all roof systems including all the accessories. 4-8 week lead time depending on the color and the profile of the metal panel

Having a relationship with a commercial roofing contractor/provider who is in good standing with both the manufacture and material distribution companies will help navigate and lessen the challenges associated with proper roof design, material supply chain disruptions, and maximation of roof life and performance.